Question # 14

The Applications Manager agreed to the acquisition by UniCo because they knew that growing Selco needed more investment than they could raise and that they personally didn’t have the skill set to move from technical leader to business leader.

Which preference does this behavior BEST display?

Options:

A.

Extravert.

B.

Introvert.

C.

Thinking.

D.

Feeling.

Buy Now
Question # 15

Which statement should be recorded under the Lessons from previous change initiatives heading?

Options:

A.

UniCo has always been seen in the marketplace as being traditional and cautious.

B.

UniCo has always successfully used customer journey mapping for educating staff in customer needs.

C.

A new software development platform is needed to integrate the new services into operational processes.

D.

The renewal of the lease for the office housing Selco staff is due in fifteen months’ time.

Buy Now
Question # 16

Awareness of the new processes in the Customer Services department is good, but so far there has been little progress on implementation with the majority of staff.

Which approach is LEAST likely to build momentum for the changes?

Options:

A.

Assign the team who facilitate new orders to take the lead in implementing new processes.

B.

Delegate responsibility for implementation to the line leadership in the department.

C.

Share the initial successes when providing mobile solutions to the Utility company.

D.

Increase the number of newsletters issued covering the strategy and delivery plans.

Buy Now
Question # 17

To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.

Which 2 statements BEST explain why the IT Support Manager is appropriate for the role of change agent for the change programme?

Options:

A.

Is good at quietly implementing directions without challenging decisions at every step.

B.

Is well-positioned to bring together other line leaders facing similar change situations.

C.

Has a strong network due to supporting all staff at all levels organization-wide.

D.

Has direct line authority over the staff who will be changing internal IT systems.

E.

Wants to gain experience in change management to improve future implementations of IT systems.

Buy Now
Question # 18

Several of the web developers working on the project have no Agile

experience. When answering the questions in the Project Approach

Questionnaire (PAQ), the Project Manager could not agree with the statement

'all members of the project understand and accept the DSDM approach'.

What action should the Project Manager take?

Options:

A.

Replace the web developers with experienced Agile practitioners.

B.

Agree with the statement in the PAQ and keep a close watch on the web

developers throughout the project.

C.

Organize a training workshop to brief all project-level and Solution

Development Team roles in the Agile approach.

D.

Accept that the web developers are experts in their field and will be

adopting their own approach throughout the project.

Buy Now
Question # 19

The Web Content Manager has provided the Web Developer with a mock up

of the 'Contact Us' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads 'Delete' instead of 'Cancel'.

What action should the Web Content Manager take?

Options:

A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Buy Now
Question # 20

Which 2 actions should the Business Visionary take to implement the new

Must Have requirement?

Options:

A.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

B.

Assess the impact of the new Must Have requirement on the original

Business Case.

C.

Source and hire a web developer with experience in developing online

financial transaction functionality.

D.

Ensure the marketing and sales teams are working together to deliver the

most effective outcome.

E.

Consolidate and circulate an agenda for the workshop.

Buy Now
Question # 21

The Business Ambassador assigned to the project is only available 2 days a

week. The Project Manager has stated that the Investigation stage for each

Timebox should, where possible, be planned around the availability of the

Business Ambassador.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because this is where any final quality control checks should be

carried out to ensure all products meet the business need.

B.

Yes, because the Investigation stage of a Timebox requires intense

engagement with the Business Ambassador.

C.

No, because it is the Refinement stage of a Timebox that requires intense

engagement with the Business Ambassador.

D.

No, because Timeboxes are only used during Evolutionary Development

and at this point the Business Ambassador is NOT required.

Buy Now
Question # 22

An external web developer is to be contracted to create the new coffee bar

insurance area on the existing web site. The chosen web developer will only

agree to work on a 'fixed price for a fixed specification' contract.

What action should the Project Manager take?

Options:

A.

Ensure the later elements of the project reflect the most valuable features

of the product being built by the contractor.

B.

Agree to a 'fixed price for a fixed specification' contract with a requirement

for the web developer to provide daily progress reports.

C.

Refuse to employ the chosen web developer as this is not an Agile

approach to project management.

D.

Divide the work into component parts to ensure the web developer is

focused on, and is paid to deliver, only what is specified for each

component.

Buy Now
Question # 23

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Buy Now
Exam Name: Agile Project Management (AgilePM) Practitioner Exam
Last Update: Feb 23, 2025
Questions: 134
AgilePM-Practitioner pdf

AgilePM-Practitioner PDF

$25.5  $84.99
AgilePM-Practitioner Engine

AgilePM-Practitioner Testing Engine

$28.5  $94.99
AgilePM-Practitioner PDF + Engine

AgilePM-Practitioner PDF + Testing Engine

$40.5  $134.99