Question # 14

John is the Scrum Master for his organization. His current project has one Development Team, but it's been decided to add two more Development Teams. What can John expect for the immediate impact on the existing Development Team's productivity?

Options:

A.

Productivity will increase.

B.

Productivity will stay the same.

C.

Productivity will decrease.

D.

It depends on the project's velocity.

Buy Now
Question # 15

While assisting the Product Owner in developing a Prioritized Product Backlog, the Scrum Master must

consider the primary factors on which the Prioritized Product Backlog is based-on. Which of the following are

those primary factors?

A) Value

B) Dependencies

C) Risk

D) Deliverables

Options:

A.

A, В, and С

B.

A

C.

A, C, and D

D.

С

Buy Now
Question # 16

While performing a cost-benefit analysis, the Product Owner of a project determined that the project has 45% probability of incurring a loss of $800,000 due to the latest Land Reform Bill. Which of the following techniques is being used by the Product Owner to perform cost-benefit analysis?

Options:

A.

Expected Monetary Value.

B.

Probability Impact Grid.

C.

Pareto Analysis.

D.

Risk Breakdown Structure.

Buy Now
Question # 17

A Product Owner is prioritizing user Stories to create a Prioritized Product Backlog for a project to design a

banking portal. All of the following User Stories will be evaluated while prioritizing EXCEPT:

Options:

A.

User Stories that generate value for the customer.

B.

User Stories that are dependent on others for completion.

C.

User Stories that are innovative and may or may not be successfully created.

D.

User Stories that are very difficult to determine its value, create and/or deliver.

Buy Now
Question # 18

Which of the following is a process in the initiate phase of Scrum?

Options:

A.

Identify Scrum Master and Stakeholder(s)

B.

Estimate User Stories

C.

Conduct Daily Standup

D.

Commit User Stories

Buy Now
Question # 19

One week passes by, and less than half of the Product Backlog (requirements) is recorded. The Product Owner believes that it's best to start the first Sprint with this information, rather than waiting for the whole backlog to be completed. What should we do?

Options:

A.

Yes it's a good time to start the first Sprint

B.

No, we should wait for the whole backlog to be completed before starting the Sprints

Buy Now
Question # 20

A company that builds propellers for ships has incurred heavy losses while implementing the product at the end of the project. This is because a large number of customer requirements which changed during the project were not incorporated into the deliverables. The company could have avoided this situation if it had applied the Scrum Methodology, as it would have ensured that any change requested by the customer was included as part of the project, and that the team produced deliverables that were better suited to the final business environment. Which Scrum aspect is being emphasized here?

Options:

A.

Value-based prioritization

B.

Appropriation

C.

Iterative development

D.

Transparency

Buy Now
Question # 21

All of the following events and activities are examples of adaptation, EXCEPT:

Options:

A.

Seeking help from team members

B.

Experienced team members mentoring new members

C.

Recording Lessons learned to improve processes and address problems

D.

Using information radiators to track the project progress

Buy Now
Question # 22

A User Story is considered complete only when the which of the following is/are satisfied?

A) Acceptance Criteria

B) Done criteria

C) Demo to the product owner

D) Non-functional criteria

Options:

A.

A and В

B.

A, В and C

C.

C and A

D.

D and A

Buy Now
Question # 23

Which of the following is true about a Prioritized Product Backlog?

Options:

A.

A Prioritized Product Backlog should not have the most valuable User Story on top, because it could be

risky.

B.

Greater value items, although potentially riskier, are given higher priority in a Prioritized Product Backlog.

C.

Uncertainty should be ruled out of the Risk-adjusted Prioritized Product Backlog.

D.

For a Sprint to succeed, User Stories picked for a Sprint should be interlinked with those selected for

subsequent Sprints.

Buy Now
Exam Code: SMC
Exam Name: Scrum Master Certified (SMC)