Special Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

RCDDv14 Exam Dumps - BICSI RCDD Certification Questions and Answers

Question # 14

In new construction, what is the percentage of pay phones that must be equipped with volume controls?

Options:

A.

4

B.

10

C.

25

D.

35

E.

50

Buy Now
Question # 15

When designing an underground conduit system, a single bend should be NO MORE THAN ________ degrees.

Options:

A.

45

B.

75

C.

90

D.

120

Buy Now
Question # 16

For a cost estimate, an ICT distribution designer should produce a document listing each task with a cost placed beside them. The type of document used is a

Options:

A.

SoW.

B.

spare ad sheet

C.

worksheet

D.

database

Buy Now
Question # 17

Exhibit:

A pay telephone using coins needs to be installed in a public area. In the specifications, it is required that the telephone shall meet the ADA (Americans with Disability Act) requirement for side reach using a wheelchair. What will be the maximum reachable height or the value of "X"?

Options:

A.

760 mm (30 in)

B.

864 mm (34 in)

C.

1170 mm (46 in)

D.

1220 mm (48 in)

E.

1370 mm (54 in)

Buy Now
Question # 18

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.

To whom should the change request be presented?

Options:

A.

The program governance board

B.

The program customer

C.

The program management office (PMO)

D.

The protect governance board

Buy Now
Question # 19

In which of the following design phases does the ICT distribution designer perform coordination with stakeholders and other disciplines (e.g.. mechanical, architectural, electrical) to ensure that the design is constructive and that any conflicts are resolved early in the process?

Options:

A.

Concept Design

B.

Design Development (DD)

C.

Schematic Design (SD)

D.

Construction Document (CD)

Buy Now
Question # 20

A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program

As a result, the program manager must do which of the following'?

Options:

A.

Utilize team members that are currently available, even though they do not have the expertise needed.

B.

Assign the tasks on the critical path to the resources available to adhere to the project schedule

C.

Delay the start of the program until the assigned resources are available

D.

Apply resource leveling considering the constraints of time, budget, and quality

Buy Now
Question # 21

Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?

Options:

A.

Verify the equipment controls are in the proper operating position.

B.

Train workers to perform the LOTO process.

C.

Apply appropriate tags both locally and remotely.

D.

Confirm the device is de-energized by proving it will not run when started.

E.

Confirm all unnecessary items have been removed from the area.

Buy Now
Question # 22

A program manager is working on benefits. The program team created and updated a benefits register earlier in the program. The benefits register should include which of the following?

Options:

A.

List of planned benefits, earned value (EV) and responsible person

B.

List of planned benefits, measurement method, and component mapping

C.

List of planned benefits, benefit creator and realization date

D.

List of planned benefits, stakeholders, and risk level

Buy Now
Question # 23

A program manager is concerned that a program will be unable to achieve its intended benefits. How should the program manager handle this concern?

Options:

A.

Meet with the program management office (PMO) lo review critical program success factors.

B.

Meet with the component project managers to reallocate resources within the program

C.

Meet with the program stakeholders to determine if a reduction in program scope is acceptable

D.

Meet with the component project managers to perform risk analysis

Buy Now
Exam Code: RCDDv14
Exam Name: BICSI Registered Communications Distribution Designer - RCDDv14
Last Update: Apr 3, 2025
Questions: 288
RCDDv14 pdf

RCDDv14 PDF

$25.5  $84.99
RCDDv14 Engine

RCDDv14 Testing Engine

$28.5  $94.99
RCDDv14 PDF + Engine

RCDDv14 PDF + Testing Engine

$40.5  $134.99