You are the Scrum Master of a Scrum Team that is new to Scrum. The Product Owner comes to you halfway through the Sprint and says, "l do not feel like the De-velopers will be able to meet the forecast that they developed during Sprint Planning." What should you do in this situation?
(choose the best answer)
You are a Scrum Master and one of the Developers approaches you and says: Every Sprint we are not completing regression testing for all of the selected Product Backlog items in the Sprint, but regression testing is part of the Definition of Done. We have discussed with the Product Owner and during the Sprint we decided to change the Definition of Done to remove regression testing. Which two actions are appropriate in this situation?
(choose the best two answers)
Five new Scrum Teams have been created to build one product. A few of the Developers ask the Scrum Master who will coordinate the work between the different Scrum Teams. What should the Scrum Master do?
(choose the best answer)
Scrum requires a Definition of Done. Which phrases describe the purpose of the Definition of Done?
(choose the best three answers)
In an environment where user acceptance testing is required before the Increment can be put into production, a development manager proposes to have user acceptance testing done every third Sprint, because the feedback from the user acceptance tests are disrupting work in Sprints. Is this a good idea?
(choose the best answer)
You are the Scrum Master for four Scrum Teams working from the same Product Backlog. Several of the Developers come to you complaining that work identified for the upcoming two Sprints will require full time commitment from Stella, an external specialist who is not a member of any of the four Scrum Teams. What would you consider acceptable solutions for the problem?
(choose the best three answers)
You are the Scrum Master for four teams working from the same Product Backlog. Several of the Developers come to you complaining that work identified for the upcoming two Sprints will require full time commitment from Phil, an external specialist. As the Scrum Master what should you do to solve this upcoming problem?
(choose the best answer)
A Scrum Team is struggling over the fact that not all Developers work full time and that other Developers regularly work from home. To solve the difficulties in aligning daily, at the Sprint Retrospective two Developers suggest having the Daily Scrum every three days, when everyone is in the office.
What would be three key concerns if the frequency of the Daily Scrum were to be lowered?
(choose the best three answers)