Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PSK-I Exam Dumps - Scrum Professional Scrum with Kanban Questions and Answers

Question # 14

Scrum Teams using Kanban can start to increase predictability by:

Options:

A.

Visualizing the Workflow using a Kanban board.

B.

Improving transparency by having a CFD: Control Chart and Aging chart.

C.

Reducing the amount of work in progress by introducing Work in Progress (WIP) Limits.

D.

Inspecting and adapting the Product Backlog during the Sprint Review.

Buy Now
Question # 15

Which of the following are lagging indicator metrics?

(choose the best three answers)

Options:

A.

Velocity.

B.

Cycle Time.

C.

Work in Progress.

D.

Throughput.

E.

Work Item Aging.

Buy Now
Question # 16

Which of these statements about Sprints and Kanban is NOT correct?

Options:

A.

A Scrum Team will eventually stop using Sprints if they correctly implement Kanban.

B.

The Sprint is an example of an explicit policy for how a team is working.

C.

The Sprint is an example of limiting Work in Progress (WIP).

D.

The Sprint is an example of a cadence.

Buy Now
Question # 17

A Service Level Expectation (SLE) consists of which two items?

(Choose the best two answers)

Options:

A.

A period of elapsed days.

B.

A cost of delay.

C.

A probability.

D.

A forecasted date.

Buy Now
Question # 18

When using Kanban, it is useful to have explicit policies. What existing elements in the Scrum Guide might be used as explicit policies?

Options:

A.

Definition of Done.

B.

Definition of Ready.

C.

Product Backlog refinement.

D.

All of the above.

Buy Now
Question # 19

True or False: Little's Law is used to forecast a Scrum Team's output.

Options:

A.

True

B.

False

Buy Now
Question # 20

Which of these statements about Sprints and Kanban is NOT correct?

(choose the best answer)

Options:

A.

The Sprint is an example of a cadence.

B.

A Scrum Team will eventually stop using Sprints if they correctly implement Kanban.

C.

The Sprint is an example of limiting Work in Progress (WIP).

D.

The Sprint is an example of an explicit policy for how a team is working.

Buy Now
Question # 21

What is the best chart to determine when a single item that has not been started will be

finished?

(choose the best answer)

Options:

A.

Cycle Time scatterplot.

B.

Cumulative Flow diagram (CFD).

C.

Throughput run chart.

D.

WIP Aging chart.

Buy Now
Question # 22

What flow metric best indicates when multiple items from the Product Backlog will be finished?

Options:

A.

Throughput.

B.

Cycle Time.

C.

Work Item Age.

D.

Work in Progress (WIP).

Buy Now
Question # 23

Within the same Kanban system, Work in Progress (WIP), is NOT a leading indicator for:

(choose the best answer)

Options:

A.

Throughput.

B.

Story points delivered.

C.

Cycle Time.

D.

Number of Product Backlog items finished in a Sprint.

Buy Now
Exam Code: PSK-I
Exam Name: Professional Scrum with Kanban (PSK 1) Exam
Last Update: Feb 22, 2025
Questions: 73
PSK-I pdf

PSK-I PDF

$25.5  $84.99
PSK-I Engine

PSK-I Testing Engine

$28.5  $94.99
PSK-I PDF + Engine

PSK-I PDF + Testing Engine

$40.5  $134.99