What needs to happen when new detailed requirements are added to a timebox?
Requirements of a similar level of effort should be removed
More people should be added to the delivery team
The delivery milestones should be reviewed and re-planned
Formal change control should be applied
Which statement about the ‘directing a project’ process is CORRECT?
The project board may pull reports from the information radiator
As a minimum, the project board should receive oral reports from the project manager
The project board should attend the delivery team’s daily stand up meeting
The project board should receive regular reports focusing on cost and time overruns
Which is a key objective of running a workshop?
To make daily progress visible to the delivery team and key stakeholders
To encourage collaboration and create the defined outputs from the event
To communicate decisions to the wider stakeholder community
To make day-to-day decisions on behalf of the delivery team within a sprint