Scenario: Eight Twelve
Eight Twelve has retail outlets throughout North America. An Enterprise Architecture practice already exists in Eight Twelve. Now the CEO and CIO decide that they want to use TOGAF9 to re-architect their Enterprise Architecture to cater to the changing strategies of Eight Twelve to better respond to the changes in the economic and technology environments.
Some of the key issues which need to be addressed in this re-architecting work are:
1. Since Eight Twelve’s retail chain operate 24 hours a day and are expanding to South America and Europe, the retail chain business ecosystem should be able to withstand any unforeseen disruptions which might affect the chain’s day to day operations. This is highly critical to ensure high levels of customer satisfaction and thus maintaining and enhancing Eight Twelve’s revenue chain.
2. Dependency between the application components, which are the nerve centers to Eight Twelve’s sophisticated range of services both external and internal, and the application platform and technology infrastructure should be minimal. This would facilitate scalability and ease of enhancement of the service offerings.
3. Eight Twelve uses the ARTS Data Model and the quality of data is of utmost importance for its operation.
4. Users of the Enterprise Information ecosystem should have an environment which is able to cater to their needs without any undue delays.
Which one of the following set of Architecture Principles do you feel is the most appropriate for these guidelines stated above for the TOGAF 9 architecting work which Eight Twelve is embarking on?
Scenario: Rollins Manufacturing
Please read this scenario prior to answering the question
Rollins Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own Manufacturing Requirements Planning (MRPII) system, production scheduling, and custom developed applications that drive the automated production equipment at each plant.
Rollins is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current MRPII and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Rollins Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their MRPII and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Rollins Manufacturing Scenario
You are serving as the Lead Enterprise Architect of the newly-formed Common ERP Deployment architecture project team.
As the Common ERP Deployment architecture project team assembles for its initial meeting, many of the participants have voiced concerns about the sweeping scope of the initiative. Others are confident that they know a solution that will work. During the meeting, a number of alternative recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team evaluates different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?
Scenario: Sollace Manufacturing
Please read this scenario prior to answering the question
Sollace Manufacturing is a major supplier in the automotive industry, headquartered In Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
Sollace Manufacturing is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff. The Sollace Manufacturing Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9. At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation. The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their planning and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Sollace Manufacturing Scenario
You are serving as the Lead Enterprise Architect for the Common ERP Deployment architecture project. One of the earliest initiatives in the Enterprise Architecture program at Sollace Manufacturing was the definition of a set of IT principles and architecture principles that are well aligned with the overall enterprise principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution. [Note: You should assume that Sollace Manufacturing has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.] Based on TOGAF 9, which of the following is the best answer?
Scenario
Please read this scenario prior to answering the question
You have been appointed as a consultant to the Chief Enterprise Architect of a multinational pharmaceutical corporation. The corporation includes 30 subsidiary companies with operations in over 60 countries and products sold in over 125 countries. It has major research and development sites in over 45 locations worldwide.
The management team is deeply committed to ensuring that the corporation is a world leader in socially responsible pharmaceutical development with a business strategy that focuses on profitability through environmentally friendly operating processes as well as a commitment to disease eradication.
The operations of the corporation are subject to legal and regulatory requirements for each country where they operate. The production of prescription pharmaceutical products has governmental controls that are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was conducting a clinical trial for a new regulated drug.
The Governing Board is concerned about the risks posed in this complex global environment. As a result the Chief Executive Officer (CEO) has appointed a Chief Compliance Officer (CCO) to be responsible for overseeing and managing compliance issues for the corporation. The CCO reports directly to the CEO.
The CCO has approved the expenditure of resources to establish an Enterprise Architecture program. He has requested to be informed about the status of projects that could impact regulatory compliance. He also wants the corporate legal staff and auditors to analyze all proposed architectures to ensure that they are within the legal guidelines for each country. In addition, the research organization should be able to see that the architecture is appropriate for its needs.
TOGAF 9 has been mandated as the framework for the development and evolution of the Enterprise Architecture practice. The Preliminary Phase has been completed to establish the enterprise architecture capability for this project.
Refer to the Scenario
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Chief Compliance Officer, legal staff, auditors and the research organization.
Based on TOGAF, which of the following is the best answer?
Scenario
Please read this scenario prior to answering the question
You are serving as the Lead Architect for the Enterprise Architecture team at a multinational company. The company has grown rapidly by acquisition and has inherited numerous supply chain processes and related IT systems. Several supply chain processes have had problems related to the timing of purchases, which has led to excess inventory. The Vice President in charge of Supply Chain Management has made the decision to consolidate and reduce redundant processes and systems. The company will move to a "Just-in-time" supply chain management so as to keep inventory costs low.
The TOGAF standard is followed for internal Enterprise Architecture activities. This project is using an iterative approach for executing the Architecture Development Method (ADM).
At present, there are no architectural assets in the Architecture Repository related to this initiative. All assets will need to be acquired, customized, or created. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving the existing supply chain management processes or systems.
The architecture development project has completed Phase A and has started a number of iteration cycles to develop the Architecture. As a packaged application is being considered, the next iteration will include both the Business and Application Architectures. Key stakeholder concerns that should be addressed by these architectures include:
1. What groups of people should be involved in the supply chain management-related business processes?
2. What non-supply chain management applications will need to be integrated with any new supply chain management applications?
3. What data will need to be shared?
Refer to the Scenario
[Note: You may need to refer to the Architectural Artifacts chapter, section 31.6 (located in Part IV) of the reference text in order to answer this question.]
You have been asked to identify the most appropriate catalogs matrices and diagrams to support the next iteration of Architecture development.
Based on the TOGAF standard, which of the following is the best answer?
Please read this scenario prior to answering the question
You are serving as the Lead Architect for a chain of convenience stores, operating as a franchise, which has over 5000 retail outlets throughout the Asia-Pacific region. The stores operate 24 hours a day and 7 days a week and rely on point-of-sale technology to manage their inventory.
Stores place all orders on-line. The back-office systems collect real-time data to support ordering and product selection decisions including the tailoring of product assortment based on sales history, customer demographics as well as the next day's weather forecast. In many cases, several stores are located in neighboring areas. This strategy makes distribution to each store cheaper, as well as making multiple deliveries per day possible.
An Enterprise Architecture practice exists within the company, with the CEO and CIO as joint sponsors. They have decided to adopt TOGAF 9 within the practice and the first project is to restructure the Enterprise Architecture so that it can better accommodate the changing strategies within the company and also better respond to changes in economic and technical environments.
The CIO has stated that the following issues need to be addressed in the restructuring:
The systems should be able to withstand any unforeseen disruptions which might affect day to day operations. This is highly critical for ensuring high levels of customer satisfaction and maintaining and growing revenue.
Dependencies between the application components, the application platform, and technology infrastructure should be minimal and well defined. This will facilitate scalability and ease of enhancement of the service offerings.
The company is adopting the ARTS Operational Data Model and Data Warehouse Model from the National Retail Federation. This will address past problems with data quality and inconsistent data.
To remain competitive, new products and promotions must undergo market trials and if these are successful, deployed across the retail chain. Information systems must be able to manage changes and updates without undue delays.
Refer to the Scenario
[Note: You should assume that the company has adopted the example set of principles that are listed and defined in TOGAF, Section 23.6. You may need to refer to Chapter 23 of the reference text in order to answer this question.]
You have been asked to identify the most relevant architecture principles for the current situation.
Based on TOGAF, which of the following is the best answer? [Note: The ordering of the principles listed in each answer is not significant.]