Question # 44

When the power density of a single cabinet is greater than 10kl/R, which cooling form is recommended ()

Options:

A.

Room-level air conditioning

B.

Row-level air-conditioning horizontal air supply airtight channel.

C.

Unsealed channel for horizontal air supply of row-level air conditioner

D.

Downstream air from room-level air conditioners

Buy Now
Question # 45

The management software recommends that the optimal location of the server installation is not considered ( ).

Options:

A.

Cabinet load

B.

Cabinet Capacity

C.

Network Bandwidth

D.

Electrical load capacity

Buy Now
Question # 46

A project requires the management system to access a third-party generator set, two smart meters 1 (same model), and two precision air conditioners (same model), then the management

system needs to report () a third-party equipment access fee ? (

Options:

A.

1

B.

3

C.

5

D.

None of the above is true

Buy Now
Question # 47

The root standard stipulates that the voltage drop of the AC cable should be controlled within 3%. It is recommended that the voltage drop of the AC cable should be controlled within ( ) when designing the UPS system.

Options:

A.

0.02

B.

0.05

C.

0.03

D.

0.01

Buy Now
Question # 48

In PDU8000, what are the optional functions (

Options:

A.

Input switch remote tripping function

B.

Temperature Monitoring Feature Function

C.

Branch switch hot swap function

D.

9 earthquake resistance

Buy Now
Question # 49

The cooling capacity of intelligent temperature control products can only be determined when the working conditions are clarified. There are many factors that affect the cooling capacity. For example, when selecting a row-level chilled water intelligent temperature control

product, at least information such as ( ) must be specified.

Options:

A.

Return air temperature

B.

Return air humidity

C.

Inlet water temperature

D.

Return water temperature

E.

Altitude

F.

Length of connecting pipe

Buy Now
Question # 50

Which of the following functions or components does the UPS5000-E (50kVA power module) come standard with? ( )

Options:

A.

SNMP function

B.

Dry contact communication card

C.

Parallel function

D.

Bus synchronization control function

Buy Now
Question # 51

Which of the following modules does the UPS5000-E include that can support hot swapping? ( )

Options:

A.

Control Module

B.

Power Module

C.

Bypass Module

Buy Now
Question # 52

The NetEcoo6000 management system can provide monitoring of the cooling power system, and which of the following functions can it provide? (Multiple choice)

Options:

A.

The power distribution system topology diagram can be provided, and the power distribution system diagram of the entire computer room can be displayed

B.

Support the display of key equipment indicators on the power distribution topology diagram, which is convenient for users to understand the operation status of the system and important nodes

C.

It can provide the topological diagram of the chilled water system, showing the operation status of the whole system

D.

None of the above is supported

Buy Now
Question # 53

UPS system battery intelligent management can fully extend battery life. Which of the following functions does UPS2000-G-(6K 20K) battery management support? () (multiple choice)

Options:

A.

Smart Sleep

B.

Automatic floating charge conversion

C.

Temperature supplement

D.

The number of battery cells is adjustable

Buy Now
Exam Code: H19-371_V1.0
Exam Name: HCS-Pre-sales-Digital Power V1.0
Last Update: Feb 23, 2025
Questions: 653
H19-371_V1.0 pdf

H19-371_V1.0 PDF

$25.5  $84.99
H19-371_V1.0 Engine

H19-371_V1.0 Testing Engine

$28.5  $94.99
H19-371_V1.0 PDF + Engine

H19-371_V1.0 PDF + Testing Engine

$40.5  $134.99