During the configuration of the DMO for SUM, how does the tool behave if option "Do not compare table contents" is selected regarding table comparison?
Please choose the correct answer.
Response:
What SAP systems can you use for the ABAP Test Cockpit (ATC) to perform the custom code analysis for an SAP S/4HANA conversion? Note: There are 2 correct answers to this question.
You are performing an upgrade of an SAP ECC development system with SUM. What is the earliest point when the upgrade is considered complete and you can allow all dialog users to log on to the system?
Please choose the correct answer.
Response:
Which steps can SUM perform during an SAP S/4HANA conversion? Note; There are 2 correct answers to this question.
You are upgrading a three-system landscape DEV - QAS - PRD. The upgrade project contains a Unicode conversion. You have already upgraded the DEV and the QAS system but not yet the PRD system. What do you need to consider? Please choose the correct answer.
In ICNV. How database operations synchronized between the source and the target table?
You are performing an S/4HANA conversion of the development system. Which credentials do you use in which system to perform the adjustment of dictionary objects (SPDD)?
Please choose the correct answer.
Response:
You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime.
The server provides 8 CPU cores. Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center you can see 40 Process Buckets being executed in parallel.
Why are 40 Process Buckets executed in parallel?
Please choose the correct answer.
Response:
The SUM procedure stops with an error during uptime. How can you identify the current phase, the one in which SUM encountered an error?
There are 2 correct answers to this question.
Response: