New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

Vce PSP Questions Latest

Page: 8 / 11
Question 32

Time-scaled logic diagrams are

Options:

A.

Only calculated using a computer.

B.

The same as a pure-logic diagram.

C.

Used to calculate the most probable activity duration.

D.

Logic networks that are drawn to match the calendar.

Question 33

Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

Options:

A.

8 work days

B.

18 work days

C.

7 work days

D.

15 workdays

Question 34

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?

Options:

A.

to highlight a time when there are more holidays and work therefore will be slower and there will be more absenteeism

B.

to denote a time during which work may not progress as fast as planned and cost and risk may be elevated

C.

to provide a key to co-a weather for safety meetings

D.

to show a difference in the calendar year

Question 35

Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?

Options:

A.

Subcontract outside forces to accelerate the Phase A Schedule

B.

Allocating forces from other BILCO contracts to the toll road project

C.

Proceeding with the work in advance of the environmental studies

D.

Reduce the phasing from 5 phases to 3 phases

Page: 8 / 11
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Jan 11, 2025
Questions: 163
PSP pdf

PSP PDF

$25.5  $84.99
PSP Engine

PSP Testing Engine

$28.5  $94.99
PSP PDF + Engine

PSP PDF + Testing Engine

$40.5  $134.99