Time-scaled logic diagrams are
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?
Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?