Question 16

Which statement about the Sprint Goal is incorrect?

(choose the best answer)

Options:

A.

The Scrum Team commits to it.

B.

The Product Owner respects the opinions of the Developers about whether they can achieve the Sprint Goal.

C.

It helps increase focus.

D.

The Scrum Team discusses openly about alternative ways to reach it.

E.

It is only a forecast and may change within the Sprint as more is learned.

F.

If it does not seem achievable, the Developers have the courage to tell the Product Owner.

Question 17

True or False: When multiple Scrum Teams work on the same product, they should employ a "Definition of Ready" to maximize their velocity. A "Definitlon of Ready" ensures that Sprint Planning can end within its timebox. This has a positive effect on the team's velocity, as the team will have more time for productive work.

Options:

A.

True

B.

False

Question 18

During Sprint Planning, Developers work with the Product Owner to create a forecast for the Sprint. A forecast is a selection of Product Backlog items that the Developers believe are possible to get done by the end of the Sprint. Select two things that explain what done means.

(choose the best two answers)

Options:

A.

Having an Increment that could be released to end users.

B.

All work for which enough expertise and skills are present in the Scrum Team.

C.

All work performed meets the Definition of Done.

D.

All work to create an Increment that is ready for testing.

E.

All work to create an Increment that is ready for acceptance testing by the

Product Owner.

Question 19

You are a Scrum Master helping to establish five Scrum Teams that will be building a product.

You discuss with them the high level of integration that the product Increment will require by the end of their first Sprint. It is a highly anticipated product, both by consumers and by the organization. Of the options raised by the future Scrum Team members, which option do you encourage?

(choose the best answer)

Options:

A.

Each Scrum Team provides a separate Increment with the functionality added by the individual team. The Sprint Review is used to identify the work needed to integrate with the other Scrum Teams. This work is then added to the Product Backlog.

B.

Each Scrum Team delivers done Increments in its own area of responsibility. Upon functional acceptance at the Sprint Review, the code is isolated for future stabilization. The release date is adjusted according to the expected work and time of such integration phase.

C.

In the first Sprint, integration is less important. The goal is to deliver business value. Functionality that is not integrated with the work of other Scrum Teams by the end of a Sprint is still reviewed to assess its potential business value. It can still be released at the Product Owner's discretion, and silent consent of the stakeholders.

D.

All Scrum Teams agree on a shared Definition of Done that describes all work needed to deliver an Increment that is the integrated sum of the work from all Scrum Teams.

Page: 4 / 4
Exam Code: PSM-II
Exam Name: Professional Scrum Master II
Last Update: Nov 23, 2024
Questions: 74
PSM-II pdf

PSM-II PDF

$25.5  $84.99
PSM-II Engine

PSM-II Testing Engine

$28.5  $94.99
PSM-II PDF + Engine

PSM-II PDF + Testing Engine

$40.5  $134.99