Question 8

You are the Scrum Master for four Scrum Teams working from the same Product Backlog. Several of the Developers come to you complaining that work identified for the upcoming two Sprints will require full time commitment from Stella, an external specialist who is not a member of any of the four Scrum Teams. What would you consider acceptable solutions for the problem?

(choose the best three answers)

Options:

A.

Organize a release Sprint in which Stella can thoroughly check and complete all the work done in her domain before considering the work releasable.

B.

Developers with an interest in Stella's domain could volunteer to take on this work in their respective Scrum Teams.

C.

Investigate whether additional techniques or frameworks for scaling Scrum would be appropriate for these Scrum Teams.

D.

Have the Developers re-order the Product Backlog so Stella can serve one team full-time in a Sprint

E.

Merge the Scrum Teams into one large Scrum Team for the next two Sprints. When the need for Stella's expertise is over, the teams can separate again

F.

Ask Stella for a plan to hire and train additional people in her domain, and in the meantime work with the Product Owner and Scrum Teams to re-prioritize the work so that tasks not depending on Stella can be done first

G.

Create a team with Stella and identify people from the Scrum Teams to temporarily work in Stella's domain to learn to better serve the existing teams

Question 9

You are the Scrum Master for four teams working from the same Product Backlog. Several of the Developers come to you complaining that work identified for the upcoming two Sprints will require full time commitment from Phil, an external specialist. As the Scrum Master what should you do to solve this upcoming problem?

(choose the best answer)

Options:

A.

Prepare the Sprint Backlogs each day tor the teams so Phil can spend some time in each team.

B.

Allocate Phil to one team per Sprint, so that over tour Sprints every team will have had the support It requires.

C.

As needed, consult with the Developers on now they want to manage this problem and help them implement their preferred solution.

D.

Ask Phil tor a plan to hire and train additional people in nis domain, and in the meantime work with the Product Owner and Developers to re-prioritize the work so that tasks not depending on Phil can be done first.

Question 10

A Scrum Team is struggling over the fact that not all Developers work full time and that other Developers regularly work from home. To solve the difficulties in aligning daily, at the Sprint Retrospective two Developers suggest having the Daily Scrum every three days, when everyone is in the office.

What would be three key concerns if the frequency of the Daily Scrum were to be lowered?

(choose the best three answers)

Options:

A.

Opportunities to inspect and adapt the Sprint Backlog are reduced. Re-aligning is bound to become even more difficult.

B.

The Scrum Master loses the ability to update the Gantt chart properly, there by obscuring the Scrum Master's tracking of Sprint progress.

C.

Less progress information will be shared, causing the plan for the Sprint to

become inaccurate and transparency over progress toward the Sprint Goal is

reduced.

D.

Impediments are raised and resolved more slowly which might impact

productivity and progress.

E.

The Product Owner cannot accurately report progress about the state of the

forecasted work to the stakeholders.

Question 11

Another team's Scrum Master seeks your advice. The Daily Scrum always runs longer than 15 minutes. The Developers suggest splitting the Scrum Team into two teams. What is your response?

(choose the best answer)

Options:

A.

You disagree — there is not enough information to justify splitting a team into two teams. You ask if there is anything you can do to help your colleague, for example observe one of the Daily Scrums with them.

B.

You agree - this is an appropriate solution to the problem.

C.

You disagree - you tell the Scrum Master that as Scrum Master they need to manage the timebox better.

D.

You agree - splitting the team into two teams is a good strategy to allow them to learn how to run Daily Scrums quickly and effectively. Once they have learned to limit the Daily Scrum to 15 minutes, you can combine the teams again.

Page: 2 / 4
Exam Code: PSM-II
Exam Name: Professional Scrum Master II
Last Update: Nov 21, 2024
Questions: 74
PSM-II pdf

PSM-II PDF

$28  $80
PSM-II Engine

PSM-II Testing Engine

$33.25  $95
PSM-II PDF + Engine

PSM-II PDF + Testing Engine

$45.5  $130