Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

Professional Scrum Developer PSD Syllabus Exam Questions Answers

Page: 8 / 11
Question 32

Developers are blocked by an impediment in the middle of the Sprint. The impediment is outside the Developer’s control. What should they do? (choose the best answer)

Options:

A.

Cancel the Sprint.

B.

Immediately raise the issue to the Scrum Master.

C.

Complete the work that can be done and complete the remainder during the "hardening sprint".

D.

Stop using Scrum until the impediment is resolved.

E.

Drop the Product Backlog items affected by the impediment from the Sprint Plan.

Question 33

Which of the following is required by Scrum? (choose the best answer)

Options:

A.

Sprint Retrospective

B.

Developers must stand up at the Daily Scrum.

C.

Sprint Burndown Chart.

D.

Release Planning.

E.

All of the above.

Question 34

What is the commitment for the product backlog?

Options:

A.

Product goal

B.

Sprint goal

C.

Sprint planning outcome

D.

Definition of done

Question 35

Which metric is least useful when measuring code maintainability?

Options:

A.

Function points

B.

Cyclometic complexity

C.

Depth of inheritance

Page: 8 / 11
Exam Code: PSD
Exam Name: Professional Scrum Developer 1 (PSD I)
Last Update: Nov 21, 2024
Questions: 163
PSD pdf

PSD PDF

$28  $80
PSD Engine

PSD Testing Engine

$33.25  $95
PSD PDF + Engine

PSD PDF + Testing Engine

$45.5  $130