Question 24

By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

Options:

A.

Acceleration.

B.

Production output.

C.

Productivity loss.

D.

Productivity efficiency.

Question 25

Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

Options:

A.

These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.

B.

These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.

C.

The activities occur in series with a 15-day lag.

D.

The activities run concurrently.

Question 26

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

Options:

A.

Detailed listing of working days for each calendar used

B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.

Assigned party responsibility for each work task

D.

Tabular listing of activities showing duration, calendar ID, early and late dates

Question 27

Which is NOT an industry-recognized methodology for quantifying critical delay?

Options:

A.

Gantt Chart.

B.

Periodic Windows.

C.

Collapsed As-Built.

D.

Time Impact.

Page: 6 / 11
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Jan 11, 2025
Questions: 163
PSP pdf

PSP PDF

$25.5  $84.99
PSP Engine

PSP Testing Engine

$28.5  $94.99
PSP PDF + Engine

PSP PDF + Testing Engine

$40.5  $134.99