Question 28

Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?

Options:

A.

19 Sep 2021

B.

08 Sep 2021

C.

09 Sep 2021

D.

27 Aug 2021

Question 29

An earned value-based project control system can use either of which two budgets as the basis of its calculations?

Options:

A.

Labor hours or dollars.

B.

Direct or indirect cost.

C.

Earned or budgeted cost yearly.

D.

Linear feet or dollars.

Question 30

Which of the following phases does NOT describe the commonly accepted construction life cycle?

Options:

A.

Claims and disputes phase.

B.

Installation phase.

C.

Planning and design phase.

D.

Turnover and start-up phase.

Question 31

The linear scheduling velocity diagram has the following two-axis:

Options:

A.

Location and crew size

B.

Time and location

C.

Time and rate of progress

D.

Time and crew size

Page: 7 / 11
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Jan 11, 2025
Questions: 163
PSP pdf

PSP PDF

$25.5  $84.99
PSP Engine

PSP Testing Engine

$28.5  $94.99
PSP PDF + Engine

PSP PDF + Testing Engine

$40.5  $134.99