Question 16

The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.

Options:

A.

uses arrows to signify logic in a network

B.

allows more than one critical path to be represented

C.

can be used to calculate the late start and late finish of all activities

D.

allows multiple relationship types to be associated with activities

Question 17

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

Options:

A.

3.9% (1 : 25.708)

B.

2.3% (1 : 43.501).

C.

9.1% (1 : 11.000).

D.

8.6% (1 : 11.591)

Question 18

What is the remaining work duration of Active D?

Options:

A.

4.

B.

11

C.

8.

D.

3.

Question 19

Determine the correct formula and date for the late finish for Activity 2002.

Options:

A.

LS.2003 - 1 day -> 11.06.01.

B.

LS.2003 - 1 day -> 10-06-01.

C.

LS.2003 + 1 day -> 10-07-01.

D.

LS.2003 - 1 day -> 10-05-01.

Page: 4 / 11
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Jan 11, 2025
Questions: 163
PSP pdf

PSP PDF

$25.5  $84.99
PSP Engine

PSP Testing Engine

$28.5  $94.99
PSP PDF + Engine

PSP PDF + Testing Engine

$40.5  $134.99