Question 12

An Adobe Workfront System Administrator has been asked to configure timesheet profiles that generate automatically and are sent to managers for approval.

Which two elements of timesheet profiles need to be configured to accomplish this accurately? (Choose two.)

Options:

A.

Specify time interval of automatic timesheet generation (i.e., weekly)

B.

Set approver field to Their Manager"

C.

Provide detailed description of the timesheet profile

D.

Specify projects to appear on the timesheet

Question 13

A System Administrator would like to export all of the calculated custom fields and the associated custom expressions from their Workfront instance to an excel file so that they can create a data dictionary for better governance of their custom data.

How would a System Administrator achieve this?

Options:

A.

Use Kick Starts to export Custom Data to Excel

B.

Create a Parameter report filtered to Parameter Type = Calculated and export to Excel

C.

Go to the Custom Forms area of Workfront in the setup panel and export all fields to Excel

Question 14

A project team has configured a Kanban board with columns for backlog, in progress, on hold, and completed statuses. The project manager wishes to automatically archive cards that have been closed for longer than two weeks.

What should the project manager change in order to make this happen?

Options:

A.

Select Configure > select Cards and enable a two week Card Falloff for the Closed column.

B.

Select the Closed column > select Edit and set Archive Limit to two weeks

C.

Select the three ellipses next to the board name > select Archive and set for two weeks.

Question 15

A marketing agency uses Workfront to plan and execute projects for their clients. Each project is associated with a Portfolio to represent the client and a Program to represent the year that the work was completed. A team leader has asked for a list report that shows the actual revenue for each Project and the total actual revenue for each client.

How would a Workfront Developer achieve this?

Options:

A.

Create a project report and add actual revenue as a column to the report review, set to summarize by sum. Apply a grouping to the report to group by portfolio name

B.

Create a project report and add actual revenue as a column to the report review and set to summarize by count. Apply a grouping to the report to group by portfolio name

C.

Create a project report and add actual revenue as a column to the report review. Apply a grouping to the report to group by portfolio name.

Page: 3 / 5
Exam Code: AD0-E908
Exam Name: Adobe Workfront Core Developer Professional
Last Update: Nov 24, 2024
Questions: 70
AD0-E908 pdf

AD0-E908 PDF

$25.5  $84.99
AD0-E908 Engine

AD0-E908 Testing Engine

$28.5  $94.99
AD0-E908 PDF + Engine

AD0-E908 PDF + Testing Engine

$40.5  $134.99