Question 68

What phase of the integrative process gives the team the greatest chance of success in meeting the project's environmental goals cost-effectively?

Options:

A.

Design

B.

Discovery

C.

Operations

D.

Construction

Question 69

The LEED AP is leading the first design charrette for a new LEED project with the project's owners. What document should be used to record the project goals to be used throughout the design of the project?

Options:

A.

Owner's Project Requirements (OPR)

B.

Owner's list of wants and needs

C.

Criteria for contractor selection

D.

Basis of Design (BOD)

Question 70

Showers are addressed under which prerequisites and/or credits within LEED Building Design and Construction?

Options:

A.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Credit, Indoor Water Use Reduction; and Location and Transportation Credit, Bicycle Facilities

B.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Prerequisite, Outdoor Water Use Reduction; and Water Efficiency Credit, Water Metering

C.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Prerequisite, Outdoor Water Use Reduction; and Location and Transportation Credit, Bicycle Facilities

D.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Credit, Cooling Tower Water Use; and Water Efficiency Credit, Water Metering

Question 71

What is the system boundary that a building life cycle analysis must be defined to account for?

Options:

A.

Cradle-to-gate

B.

Cradle-to-grave

C.

Cradle-to-cradle

D.

Cradle-to-building

Page: 17 / 19
Exam Code: LEED-AP-BD+C
Exam Name: LEED AP Building Design + Construction (LEED AP BD+C)
Last Update: Nov 21, 2024
Questions: 269
LEED-AP-BD+C pdf

LEED-AP-BD+C PDF

$28  $80
LEED-AP-BD+C Engine

LEED-AP-BD+C Testing Engine

$33.25  $95
LEED-AP-BD+C PDF + Engine

LEED-AP-BD+C PDF + Testing Engine

$45.5  $130