Which version serves as a proof of the project status in the past and also serves as a comparison with the operative project?
Please choose the correct answer.
Response:
You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?
Please choose the correct answer.
Response:
In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as?
Please choose the correct answer.
Response:
How do you derive the hierarchy of a work breakdown structure from the numbers of their WBS elements?
Please choose the correct answer.
Response:
What is the transaction code for editing the planning profile?
Please choose the correct answer.
Response:
Which type of network does not allow you to assign materials directly, but only indirectly using a bill of materials?
Please choose the correct answer.
Response:
When using budgeting and active availability control, which business transactions affect the current budget?
There are 3 correct answers to this question.
Response:
A customer wants to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you recommend?
There are 2 correct answers to this question.
Response:
If the material is not assigned to any sales order or project and are available for use by general plant requirements. We consider this under which type of stock?
There are 2 correct answers to this question.
Response:
In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?
Please choose the correct answer.
Response: