Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

ASD01 Exam Dumps - Blue Prism Solution Designer Questions and Answers

Question # 4

Consider the following high-level design.

The application concerned is prone to being sluggish or even unresponsive at times. As thesolution designer you should anticipate that there will be system exceptions and that after an exception case the application might not be in an ideal state.

What should you do? (Choose three.)

Options:

A.

Add ‘clean up’ logic to get the application in the rightposition after Apply Queue Item Result.

B.

Kill the application after each case and log back in to ensure the next case starts in the right position.

C.

Instruct the developer to build objects capable of navigating the application back to the home position.

D.

Restart the application if attempts to navigate back to the home position fail.

E.

Move Log Into Application to be before Work Step1 and move Log Out of Application to be after Step3.

F.

Add ‘clean up’ logic to get the application in the right position before Work Step1.

G.

Add ‘clean up’ logic to get the application in the right position after Work Step3.

Buy Now
Question # 5

Which of the following statements about using Work Queue designs to split a business process into a multi part robotic solution is correct?

1. Using multiple Work Queues and Processes for the different stages of the business process is a valid design option to split a business process into a multi partrobotic solution.

2. Using a single Work Queue and deferring cases for future processing is a valid design option to split a business process into a multi part robotic solution.

3. Using an item’s status to control when to work it is a valid design optionto split a business process into a multi part robotic solution.

4. You cannot split a business process into a multi part robotic solution.

Options:

A.

1 and 2 Only

B.

4 only

C.

1 and 3

D.

1, 2 and 3

Buy Now
Question # 6

A process is required for a client in the banking sector that involves using an application to transfer funds between accounts. A strong security model is in place to prevent any malicious activity but the client is nervous about the risk of external problems, like a power cut leaving a case in an incomplete state or a fault in thesource data causing a case to be duplicated or an excessively large transfer to be made.

What should be included in the solution design? (Choose three.)

Options:

A.

A different queue for each major processing step.

B.

A different process for each majorprocessing step.

C.

A single queue that is cleared of all worked items at the start of each day.

D.

Rules to limit transaction values.

E.

A key value that will uniquely identify queue items.

F.

A requirement that the solution is never run on more than onemachine.

G.

An exception handling procedure to track manual referrals.

Buy Now
Question # 7

A retail bank has promoted 2 Blue Prism processes to production:

1. Email poller

2. Customer onboarding

3. Direct DebitCancellations

One instance of the email poller process will run 24/7 feeding work queues for the other two processes.

Three instances of the Customer onboarding process will run between 6am and 11pm each day on three separate VMs.

One instance of the Direct Debit Cancellations process will run between 6am and 4pm each day on the same VM as the Email poller process.

What is the maximum number of Blue Prism licenses that will be consumed each day?

Options:

A.

3

B.

4

C.

5

D.

6

Buy Now
Question # 8

The status of a Work Queue can be used as a method of recording that work has been done so far on a Work Queue item.

Please consider the following statements:

1. For MI, to easily see how far an item has beenworked.

2. To aid manual working of exceptions, providing the Item Status can inform staff what work is still outstanding on an item that needs manually.

3. To enable Work Queue items to be safely retried, a process can use the item status to know which updates have already been performed so that they are not repeated.

4. To record the Customer’s Surname

Options:

A.

2 only

B.

2 and 3 only

C.

1, 2 and 3 only

D.

1, 2, 3 and 4

Buy Now
Question # 9

Which of the following statement combinations about Blue Prism memory management is correct?

Options:

A.

A Blue Prism Process reads a Business Object into memory as required. Once the called Action is complete, the Process releases the memory for the .Net Garbage Collector to reclaim.A Blue PrismProcess reads a Sub Process into memory as required. Once the called Sub Process is complete, the Process releases the memory for the .Net Garbage Collector to reclaim.

B.

A Blue Prism Process holds a Business Object in memory for the duration of its run.ABlue Prism Process reads a Sub Process into memory as required. Once the called Sub Process is complete, the Process releases the memory for the .Net Garbage Collector to reclaim.

C.

A Blue Prism Process holds a Business Object into memory as required.Once the called Action is complete, the Process releases the memory for the .Net Garbage Collector to reclaim.

D.

A Blue Prism Process holds a Sub Process in memory for the duration of its run.A Blue Prism Process holds a Business Object in memory for the duration of its run.

Buy Now
Question # 10

Imagine you are designing the application integration logic for a solution. One of the applications involved is one you have not automated before but it is widely used and the project is the first in a series for this client.

Which of the following are valid considerations when designing business objects? (Choose two.)

Options:

A.

It’s best that objects are designed to be reusable and are not made bespoke for one process.

B.

The first Production process to automate an application should not share its integration logic with any other because there will invariably be teething problems during an initial implementation.

C.

When an application is automated for the first time a single business object should be used to isolate the first process from any that follow.

D.

Any new application should be assessed to find the appropriate integration technique and identify any potential technical issues.

E.

It’s best that each process usesits own business objects to keep it separate from any other.

Buy Now
Question # 11

Consider the following steps for a theoretical manual process.

  • Check in input folder any newfiles.
  • If there are no files check again later as files can arrive anytime, and there is no limit to the number of files that may come.
  • Open the next available file.
  • Take the first case.
  • Start System X and find the case details.
  • If the case can’t be found, move to the next one.
  • After finding the case in System X, fetch additional case details from System Y.
  • Again if the case can’t be found, move to the next one.
  • Analyse all the data to see if System Z should be updated.
  • If the data does not meet the requirements, add notes indicating this to System X and Y and move to the next case.
  • If the data does meet the requirements, update the case in System Z.
  • Add notes to System X and Y and move to the next case.
  • At the end of the file, go back and look for another.
  • Stop checking for new files at 16:00 and finish any remaining cases.
  • When all work is complete create a report of the day’s exception cases.
  • Close down Systems X, Y and Z.

If it is possible that there are long intervals between files arriving, what are the alternatives the process should take to control System X, System Y and System Z? (Choose two.)

Options:

A.

Nothing because they will not have been started if no files have arrived yet.

B.

Nothing, just leave them logged in until more work arrives.

C.

Minimize them to keep the desktop clear.

D.

Close Y and Z down but keep X open because it is the first application needed to work a case.

E.

Log out while waiting and log back in when a file arrives.

F.

Stop them from timing out by keeping themactive while waiting for files.

Buy Now
Exam Code: ASD01
Exam Name: Designing Blue Prism Process Solutions
Last Update: Feb 22, 2025
Questions: 27
ASD01 pdf

ASD01 PDF

$25.5  $84.99
ASD01 Engine

ASD01 Testing Engine

$28.5  $94.99
ASD01 PDF + Engine

ASD01 PDF + Testing Engine

$40.5  $134.99