A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.
What action should the task owner take?
A copywriter wants to see his incomplete tasks for projects to which he is assigned.
Which steps should the project manager take to create a custom Workfront report with this information?
What occurs when an individual enters a new commit date that is after the original planned date of a task?
A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?
Given this information regarding a Task:
Planned Start Date: May 14
Actual Start Date: May 14
Planned Completion Date: May 20
Projected Completion Date: May 22
Percent Complete: 50%
Duration: 5 Days
Planned Hours: 8 Hours
Status: In ProgressIf today's date were May 19, what would be the Task's progress status?
A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.
What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?
A project manager wants to see all of the assignees for each task in a project.
Which field should the manager reference to view all task assignees?
A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.
What steps should the project manager take to create a custom Workfront report with this information?