Question # 24

Which four actions should you take before proceeding with applying updates to your Exadata Database Machine?

Options:

A.

Consult My Oracle Support note 888828.1 to determine the current recommended Exadata software release.

B.

Check the Exadata Critical Issues My Oracle Support note 1270094.1 for any issues not added to the latest version of exachk.

C.

Run exachk and resolve only WARNINGS that you have not seen before.

D.

Run the appropriate patchmgr preqequisite check step for each component being updated.

E.

Run patchmgr --all_comp —autofix —autobackup —upgrade —rolling.

F.

For database servers, perform a server backup using patchmgr —dbnodes db_list_file —backup —rolling.

Buy Now
Question # 25

For which four component failures on an X9M Database Machine does Auto Service Request (ASR) raise service requests?

Options:

A.

RoCE network interface cards in the storage servers

B.

fans in the storage servers

C.

Cisco RDMA over Converged Ethernet (RoCE) switches

D.

RoCE network interface cards in the database servers

E.

power distribution units

F.

Cisco management switch

G.

power supplies in the database servers

Buy Now
Question # 26

An Exadata X9M-2 Elastic Rack with 4 Database Servers and 8 HC Storage Servers and 3-phase 24kVA PDUs is being installed in a Data Center. However, the Data Center is only providing enough power for a single cable from each PDU. Which statement is correct?

Options:

A.

A splitter cable can be used to provide power to all PDU cables.

B.

The power cables from the servers to the PDUs can be rearranged inside the rack following OECA guidance to utilize a single PDU power cable.

C.

The installation cannot proceed until two power feeds are available per PDU.

D.

The installation can go ahead, no change is required.

Buy Now
Question # 27

Your system administrator reports an amber, non-blinking light on one of your Exadata storage disks. You immediately execute the 'list physicaldisk where diskType=HardDisk and status=failed DETAIL' command on the Exadata storage system and the specified disk is indeed reported as failed. Platinum Support has not been enabled for this system. Enterprise Manager Cloud Control is monitoring the system.

What is the next step that you should perform before you do anything else?

Options:

A.

Ask the system administrator to replace the broken disk with a spare.

B.

Check the database to see if any rebalance operations are active.

C.

Call Oracle Support and make an appointment so that the drive can be replaced.

D.

Wait for the email of the failure that Exadata or Enterprise Manager will send.

E.

Download and run the latest exadiag tool.

F.

Wait for a blue light to appear on the disk if the rebalance operation is running.

Buy Now
Question # 28

Which two statements are true about Exadata System Software metrics and alerts on an Exadata Database Machine?

Options:

A.

Metric alerts are never stateful.

B.

Metric thresholds, if set, will persist across storage and database server reboots.

C.

SMTP metric alert notifications must be sent to both ASR manager and Enterprise Manager agents.

D.

Metric alert notifications can be sent to only one destination such as Enterprise Manager OR SNMP OR SMTP.

E.

Metrics have no thresholds set on them by default.

Buy Now
Exam Code: 1z0-902
Exam Name: Oracle Exadata Database Machine X9M Implementation Essentials
Last Update: Feb 23, 2025
Questions: 85
1z0-902 pdf

1z0-902 PDF

$25.5  $84.99
1z0-902 Engine

1z0-902 Testing Engine

$28.5  $94.99
1z0-902 PDF + Engine

1z0-902 PDF + Testing Engine

$40.5  $134.99