Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

1z0-1075-24 Exam Dumps - Oracle Manufacturing Cloud Questions and Answers

Question # 4

Which three entities must you set up in Oracle Manufacturing Cloud to create a work definition for an item that will be manufactured in-house?

Options:

A.

Resources

B.

Operations

C.

Production line

D.

Operation items

E.

Manufacturing lead time

Buy Now
Question # 5

In a manufacturing plant, two purchase components, PI and P2, and a resource, Rl, are required to assemble a product. The cost of the assembly is calculated by using the standard costing method. The work definition and resource rates for the assembly have been defined as Required.

A Cost Accountant is estimating cost of the assembly, and analyzing rolled-up costs before finally publishing estimates as frozen standards to Cost Accounting by using a Cost Planning Scenario. While reviewing rolled-up costs, the extended costs of purchase components are not included in a rolled-up scenario.

What is the reason for this?

Options:

A.

Costs for purchase components PI and P2 are not defined In Cost Accounting.

B.

Purchase components PI and P2 are not associated with the material cost plan of the Cost Planning Scenario.

C.

Create Accounting was not initiated.

D.

Create Accounting Distributions was not initiated.

Buy Now
Question # 6

Which statement is NOT true about using a Quick Complete action for an operation transaction?

Options:

A.

You can use it for simultaneous reporting of one or more transactions.

B.

It is used on serial tracked operations and non-serial tracked operations with or without inspections.

C.

You can use It to transact one or more serial numbers.

D.

You can use it to collect Inspection results.

E.

You can use it to transact only one serial number at a time.

Buy Now
Question # 7

Which statement is NOT true about cumulative lead time?

Options:

A.

It calculates cumulative manufacturing lead times by rolling up manufacturing lead times of make Items.

B.

It updates the item's lead time attributes at the end of the calculation process: cumulative manufacturing and cumulative total lead times.

C.

It calculates cumulative total lead times by rolling up lead times of make items and adding up lead time values of buy items.

D.

It updates lead time percent at the operation level in the work definition.

Buy Now
Question # 8

You have been asked to set up cost estimates for 10 different purchased items. Which two tasks can you perform to achieve this?

Options:

A.

Import a spreadsheet.

B.

Call a web service.

C.

Use the Mass Edit functionality.

D.

Run the "Update Item Cost Estimate" ESS process.

E.

Enter cost estimates directlyinto the UI.

Buy Now
Question # 9

Two work definitions are created in the application: one for Engine Finished Good and the other for Pallet Finished Good. The Engine Finished Good item should have Pallet Finished Good as one of its components.

How can you establish the relationship between the Pallet and Engine work definitions?

Options:

A.

Create a subinventory to serve as the completion subinventory for yielding Pallet, and then use the same subinventory to serve as the supply subinventory of Pallet in the work definition created for Engine.

B.

Work definition versions can be used to tie the work orders.

C.

Assign a higher priority to the work definition created for Engine and a lower one to the work definition for Pallet.

D.

The two work definitions can be tied through Project or Selban numbers.

Buy Now
Question # 10

In the work execution area, which three infolets are provided to users for instant access?

Options:

A.

Work Order Performance

B.

Scrap

C.

Operation Exception

D.

Operation Efficiency

E.

work order Exception

Buy Now
Question # 11

Your client has asked you to implement the functionality to ensure that the system checks for Qualified Operators when reporting labor usage.

Which statement is NOT true?

Options:

A.

Validation of operator qualification is also enforced when reporting operation is completed through the dispatch list.

B.

You will need to report a qualified operator to manually report resource transactions, if the resource has a job profile associated with It.

C.

Quick Complete is allowed for operations that contain resources with associated job profiles.

D.

Qualified labor must be reported at the resource train stop.

Buy Now
Question # 12

You are defining a standard operation for visual inspection. You want the completion of this standard operation to be reported in all work orders that reference it.

Which setup task must you perform to achieve this?

Options:

A.

Deselect the Count Point check box while defining the standard operation.

B.

Select the Automatically Transact check box while defining the standard operation.

C.

Select the Count Point check box while defining the standard operation.

D.

Ensure that the Charge Type of the resource is Automatic.

Buy Now
Question # 13

Your client is planning to override the Plant Production Calendar with One or More Date-Effective Work Center Calendars. You need to explain the consideration when using the Override the Plant Production Calendar with One or More Date-Effective Work Center Calendars feature.

Which three statements are true when overriding the production calendar?

Options:

A.

The Work Execution Work Area Infolets and Manage Production Exceptions page are based on the plant calendar and not on work center calendars.

B.

While defining override calendars, you need to ensure that the date effective range for a work center calendar association can be overlapping and contiguous.

C.

Even if there are override calendars, the lead time calculation in days for an item remains based on the plant calendar and not on work center calendars.

D.

When the user executes search action in the Review Dispatch List page, if more than one work center are selected and if the start date or completion date is based on Shift-based search, then the operations are queried based on the shifts of the plant calendar only.

E.

Supplier operations used in outside processing use the work center calendar in work order scheduling.

Buy Now
Exam Code: 1z0-1075-24
Exam Name: Oracle Manufacturing Cloud 2024 Implementation Professional
Last Update: Feb 18, 2025
Questions: 50
1z0-1075-24 pdf

1z0-1075-24 PDF

$29.75  $84.99
1z0-1075-24 Engine

1z0-1075-24 Testing Engine

$33.25  $94.99
1z0-1075-24 PDF + Engine

1z0-1075-24 PDF + Testing Engine

$47.25  $134.99