1z0-1066-24 Exam Dumps - Oracle Supply Chain Planning Cloud Questions and Answers

Question # 34

During implementation, the customer would like to use safety stock planning parameters. However, they would like to uncheck "Safety stock change interval to all items." What will the results be if they choose to uncheck this parameter?

Options:

A.

Safety stock will not be calculated at all for this plan.

B.

This option will require a min/max quantity for this parameter even though it will not be used.

C.

Safety stock will use a smoothing method to calculate the safety stock within change interval to determine the level of safety stock needed without this parameter.

D.

Safety stock change interval will only apply to items with Days of Cover safety stock method.

Buy Now
Question # 35

You want to be able to filter your data by the planner code attribute on the item. Where can you go to do this?

Options:

A.

Configure Planning Analytics > Levels and Attributes tab

B.

The process "Add Levels and Attributes" must be run to associate new attributes.

C.

The process "Associate Measure Catalog Attributes" must be run to associate new attributes.

D.

Enable planner code on Planning Analytics page.

E.

Configure Planning Analytics > Measure Catalog

Buy Now
Question # 36

A new product has no similar items on which to base a forecast. Which approach is a temporary solution for supply planning?

Options:

A.

There is no temporary solution.

B.

Consider safety stock based on a days-of-cover calculation.

C.

Consider a simulation of the supply plan's calculated safety stock.

D.

Use safety stock as demand, until enough shipment history is available.

Buy Now
Question # 37

You've decided to opt into the Customer Demand Collaboration feature. Which three statements describe what that enables?

Options:

A.

A customer can use B2B messaging to share their expected needs and historical consumption for the products you sell them.

B.

The information they share with you is informational and only available to you in the portal.

C.

A customer can log in to a portal and manually enter their expected needs for the products you sell them.

D.

You can post to the portal your statistical forecast for the products you sell them so they can see your forecast for them.

Buy Now
Question # 38

Which statement fully describes the contents and purpose of the Product Lifecycle Management (PLM) page layout?

Options:

A.

The PLM layout has one table to define and manage discontinuation dates, and another table for entering forecast percent changes.

B.

The PLM layout has one table to define and manage launch and discontinuation dates, and another for entering forecast adjustments.

C.

The PLM layout has two tables: one to define and manage launch dates for new products, and another for entering forecast adjustments.

D.

The PLM layout has a single table to define and manage launch dates, and also enter any forecast adjustments.

Buy Now
Question # 39

Your clients want to simulate how canceling demand may impact a plan. Which two steps must be done to simulate this change? (Choose two.)

Options:

A.

Run plan with 'Do not refresh with current data'

B.

Manage Plans > Edit Plan Options > Add simulation set

C.

Open plan > View Supplies and Demands > Firm the demand and set firm quantity to 0 > Save changes

D.

Open plan > View Supplies and Demands > Remove the sales order from the plan and firm demand > Save changes

E.

Run plan with 'Refresh with current data'

Buy Now
Question # 40

You have executed Planning Data Collection and want to confirm that data has successfully been collected. Identify the three data combinations that can be viewed using the Maintain Supply Network Model Page. (Choose three.)

Options:

A.

Customer Location and Carriers

B.

Safety Stock and Subinventories

C.

Sales Channel and Demand Class

D.

Calendar and Master Organization

E.

Supplier Site and Service Level

Buy Now
Question # 41

Which statement is correct regarding S&OP?

Options:

A.

S&OP supply requirements are based on Bills of Resources (BOR) if available; otherwise, the Work Definitions are used.

B.

Sourcing cannot be maintained directly in S&OP, but must be collected.

C.

S&OP supply requirements are only based on Bills of Resources (BOR).

D.

If Bills of Resources are used, the only way to make one available is via import using a dedicated template.

Buy Now
Question # 42

Which statement applies only to the planning of back-to-back items and not standard items?

Options:

A.

Planning analyzes supply shortages and capacity overloads using any of the standard planning tools.

B.

Must use Global Order Promising and Supply Chain Orchestration to release and create new supplies

C.

Must have added sourcing rules to the Global Order Promising assignment set.

D.

Planning pegs reserved supplies to sales orders.

E.

Planning collects bookings or shipments history to forecast items.

Buy Now
Question # 43

Your company needs to implement project-driven supply planning, along with demand and supply netting based on the country of origin. Which setup task is needed for this?

Options:

A.

Manage Demand and Supply Netting Rules task

B.

Manage Attribute-Based Netting Rules task

C.

Manage Project Netting Rules task

D.

Manage Attribute and Project Netting Rules task

Buy Now
Exam Code: 1z0-1066-24
Exam Name: Oracle Planning and Collaboration Cloud 2024 Implementation Professional
Last Update: Mar 31, 2025
Questions: 138
1z0-1066-24 pdf

1z0-1066-24 PDF

$25.5  $84.99
1z0-1066-24 Engine

1z0-1066-24 Testing Engine

$28.5  $94.99
1z0-1066-24 PDF + Engine

1z0-1066-24 PDF + Testing Engine

$40.5  $134.99