SPS Premium Exam Questions

Page: 2 / 2
Question 8

How should multiple Scrum Teams deliver a valuable and useful Increment in a Sprint?

(choose the best answer)

Options:

A.

Each Scrum Team delivers done Increments of its own area of responsibility. These

Increments are integrated into a whole product during stabilization prior to release.

B.

Each Scrum Team provides a unique done Increment that includes the team's added

functionality.

C.

Each Sprint, all Scrum Teams complete work that integrates with all of the other work

from other Scrum Teams on the initiative.

D.

Functionality not integrated with the work of other Scrum Teams may be delivered as

unintegrated Increments to demonstrate the value created by the Scrum Teams

unable to completely integrate their Increments.

Question 9

The purpose of Nexus Sprint Planning is to:

(choose the best two answers)

Options:

A.

Coordinate the activities of all the Scrum Teams in a Nexus.

B.

Discover all the dependencies between Product Backlog items.

C.

Ensure all teams are committing to the right work.

D.

Create a plan for the Sprint.

Question 10

How should Product Backlog items be chosen when multiple Scrum Teams work from the same

Product Backlog?

(choose the best answer)

Options:

A.

The Scrum Teams choose the Weighted Shortest Job First.

B.

The Developers pull work in agreement with the Product Owner.

C.

Each Scrum Team takes an equal number of items.

D.

The Scrum Team with the highest velocity pulls Product Backlog items first.

E.

The Product Owner should provide each team with its own Product Backlog.

Question 11

Scenario C: Dependencies and Product Backlog items

During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams

identify many dependencies. This makes it hard for them to choose the work they could pull

into their individual teams for the next Sprint. No matter how they reorganize the Product

Backlog items, they continually find more or new dependencies.

What techniques could help this Nexus manage their dependencies effectively?

(choose the best two answers)

Options:

A.

The Nexus Integration Team should complete the dependent work ahead of the

Sprint for the teams.

B.

Reorganize team members between the teams to eliminate cross-team

dependencies.

C.

Extend the Sprint so that the teams can have more time to complete the

dependent work.

D.

Reorder Product Backlog items to better accommodate dependencies.

Page: 2 / 2
SPS Premium Exam Questions,
Exam Code: SPS
Exam Name: Scaled Professional Scrum (SPS) Exam
Last Update: Dec 22, 2024
Questions: 40
SPS pdf

SPS PDF

$25.5  $84.99
SPS Engine

SPS Testing Engine

$28.5  $94.99
SPS PDF + Engine

SPS PDF + Testing Engine

$40.5  $134.99