Question 24

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

Options:

A.

Assign a scribe to take notes.

B.

Record the meeting and transcribe the notes later.

C.

Instruct each team member to take notes.

D.

Get a facilitator for the meetings.

Question 25

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

Options:

A.

PERT chart

B.

Milestone chart

C.

Gantt chart

D.

Budget burndown chart

Question 26

Which of the following is required to provide a hardware installation with a Tier 5 redundancy level?

Options:

A.

Storage project

B.

Computer services project

C.

Database project

D.

Multitiered architecture project

Question 27

A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Non-disclosure agreement

Page: 6 / 21
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2024)
Last Update: Nov 18, 2024
Questions: 291
PK0-005 pdf

PK0-005 PDF

$28  $80
PK0-005 Engine

PK0-005 Testing Engine

$33.25  $95
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$45.5  $130