Scaled Agile Framework SAFe-RTE Release Date

Page: 6 / 6
Question 24

What is one way Kanbans are used in SAFe?

Options:

A.

To manage queue length

B.

To manage runway cadence

C.

To manage Program Increment (Pl) Objectives

Question 25

Which activity takes place during Team Breakout #2 on the second day of Program In-crement (PI) Planning?

Options:

A.

The RTE modifies the PI Iteration schedule, if needed, based on the scope of high priority Features

B.

Business Owners assign business value without team discussion so they can nor-malize business value across all teams on the Agile Release Train

C.

All Feature delivery and dependencies are visualized on the program board

D.

The Release Train Engineer (RTE) combines all Team PI Objectives into Program PI Objectives

Question 26

Which two behaviors should a Scrum Master represent as a coach? (Choose two.)

Options:

A.

Provide subject matter expertise

B.

Lay out the team's plan for the iteration

C.

Encourage the team to learn from their mistakes

D.

Set long-term goals for the team

E.

Focus on deadlines and technical options

Question 27

Which of the following is true about the ART sync event?

Options:

A.

It is run after PO-sync and Scrum of Scrum events

B.

It is a combination of PO-sync and Scrum of Scrums events

C.

It occurs during the Innovation and Planning iteration

D.

Attendance by the entire ART is important

Page: 6 / 6
Exam Code: SAFe-RTE
Exam Name: SAFe Release Train Engineer (RTE)
Last Update: Dec 26, 2024
Questions: 180
SAFe-RTE pdf

SAFe-RTE PDF

$25.5  $84.99
SAFe-RTE Engine

SAFe-RTE Testing Engine

$28.5  $94.99
SAFe-RTE PDF + Engine

SAFe-RTE PDF + Testing Engine

$40.5  $134.99