Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

Project+ PK0-004 Updated Exam

Page: 20 / 29
Question 80

The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project.

Which of the following schedule compression techniques should be used by the project manager?

Options:

A.

Rescheduling

B.

Crashing

C.

Rebaselining

D.

Control scope

Question 81

A project manager wants to determine the percentage of a project's budgeted costs versus expenditures.

Which of the following calculations should the project manager perform?

Options:

A.

Burn rate

B.

Critical path analysis

C.

EV

D.

EAC

Question 82

Which of the following is an example of quantitative risk management?

Options:

A.

Prioritizing risk mitigation response procedures

B.

Determining annual loss expectancy

C.

Sorting risks into three categories

D.

Assigning an owner to each identified risk

Question 83

A project team is executing a transition plan for a project. During which of the following project phases does this normally occur?

Options:

A.

Execution

B.

Monitor and control

C.

Closing

D.

Planning

E.

Initiation

Page: 20 / 29
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Nov 18, 2024
Questions: 796
PK0-004 pdf

PK0-004 PDF

$28  $80
PK0-004 Engine

PK0-004 Testing Engine

$33.25  $95
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$45.5  $130