Project+ PK0-004 Passing Score

Page: 22 / 29
Question 88

A project has been created, and the project team has been identified. Which of the following is the NEXT step?

Options:

A.

Release an article on the company blog.

B.

Conduct a company town hall.

C.

Host a kickoff meeting.

D.

Post a notice on social media.

Question 89

Which of the following would MOST likely be considered a project?

Options:

A.

Performing scheduled maintenance

B.

Picking and shipping a warehouse order

C.

Troubleshooting a company-wide network issue

D.

Remodeling a house

Question 90

The project team is creating a schedule for an upcoming project and attempting to determine when each task should occur.

Which of the following will assist the project team with building the schedule?

Options:

A.

Task sequencing

B.

Task predecessors

C.

Task dependencies

D.

Task prioritizing

Question 91

A project sponsor wants to know which tasks are next in the project but is unable to find this information.

Which of the following may need to be adjusted?

Options:

A.

Scope document

B.

Status report

C.

Issue log

D.

Risk log

Page: 22 / 29
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Nov 18, 2024
Questions: 796
PK0-004 pdf

PK0-004 PDF

$28  $80
PK0-004 Engine

PK0-004 Testing Engine

$33.25  $95
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$45.5  $130