Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

Project+ PK0-004 Book

Page: 4 / 29
Question 16

Given the following sprint:

Which of the following charts BEST demonstrates the decreasing number of Not Started items for the sprint depicted above?

Options:

A.

Gantt chart

B.

Pareto chart

C.

Scatter chart

D.

Burndown chart

Question 17

A project manager has received numerous complaints from staff concerning poor service provided by a vendor.

Which of the following steps should the project manager take FIRST to correct the problem?

Options:

A.

Review the SOW with the vendor and terminate the vendor

B.

Notify the key stakeholders of the problem and send a C&D letter to the vendor

C.

Notify the vendor of the complaints and review the SLA with the vendor

D.

Review the acceptable use policy with the vendor before requesting termination of the vendor’s employee.

Question 18

A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?

Options:

A.

Incident response

B.

Quality control

C.

Resource changes

D.

Business continuity response

Question 19

A project team is identifying, rating the probability of, and determining the impact on potential problems throughout the project. The team is also including the corresponding actions to take.

Which of the following activities does this describe?

Options:

A.

Risk identification

B.

Risk quantification

C.

Risk planning

D.

Risk qualification

Page: 4 / 29
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Nov 18, 2024
Questions: 796
PK0-004 pdf

PK0-004 PDF

$28  $80
PK0-004 Engine

PK0-004 Testing Engine

$33.25  $95
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$45.5  $130