Why is change management important in a project?
Which statement BEST describes how approved plans enable control?
How is Uncertainty Identified, assessed and controlled?
Which TWO are objectives of the ‘starting up a project’ process?
1. To provide an interface between the corporate layer and the project
2. To provide the required authority to initiate the project
3. To plan the work required for project initiation
4. To provide business justification for initiating the project