Question 40

Expenditure tracking helps with cost:

Options:

A.

reporting

B.

scheduling

C.

discounting

D.

floating

Question 41

A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

Options:

A.

Add durations.

B.

Add the start and finish dates

C.

Add tasks.

D.

Add resources.

Question 42

A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:

Options:

A.

internal project team.

B.

key stakeholders.

C.

affected team members.

D.

full project team.

Question 43

Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?

Options:

A.

SCRUM retrospective meeting

B.

Sprint planning meeting

C.

Daily standup meeting

D.

Review meeting

Page: 10 / 29
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Nov 18, 2024
Questions: 796
PK0-004 pdf

PK0-004 PDF

$28  $80
PK0-004 Engine

PK0-004 Testing Engine

$33.25  $95
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$45.5  $130