Question 64

A Scrum Master is essentially the same thing as a traditional PM (Project Manager).

Options:

A.

True

B.

False

Question 65

Which two ways of creating Scrum Teams are consistent with Scrum's values?

(choose the best two answers)

Options:

A.

Bring all the people together and let them organize into Scrum Teams

B.

Managers personally re-assign current subordinates to new teams.

C.

Existing teams propose how they would like to go about organizing into the new

structure.

D.

Managers collaborate to assign individuals to specific teams.

E.

The Chief Product Owner determines the new team structures and assignments.

Question 66

True or False: A scrum Master Fulfills me same role as a traditional project Manager.

Options:

A.

True

B.

False

Question 67

A Scrum Master is introducing Scrum to a new Team. The Team has decided that a Sprint

Retrospective is unnecessary. What action should the Scrum Master take?

(choose the best answer)

Options:

A.

Comply with the decision of the self-managing team.

B.

Begin facilitating productive and useful Sprint Retrospectives.

C.

Call a meeting between the ScrumTeam and senior management

D.

Consult with the Product Owner to see how they feel about the situation.

Page: 16 / 18
Exam Code: PSM-I
Exam Name: Professional Scrum Master I
Last Update: Nov 23, 2024
Questions: 250
PSM-I pdf

PSM-I PDF

$25.5  $84.99
PSM-I Engine

PSM-I Testing Engine

$28.5  $94.99
PSM-I PDF + Engine

PSM-I PDF + Testing Engine

$40.5  $134.99