Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

Pearson PK0-005 New Attempt

Page: 16 / 21
Question 64

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

Options:

A.

ROI.

B.

SOW.

C.

RFI.

D.

RPR

Question 65

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

Options:

A.

Responsibility assignment matrix

B.

Acceptable communication channels

C.

Risk registry

D.

Staff directory

Question 66

A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?

Options:

A.

Flat

B.

Projectized

C.

Weak matrix

D.

Functional

Question 67

A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?

Options:

A.

Project network diagram

B.

Gantt chart

C.

Issue log

D.

Risk report

Page: 16 / 21
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2024)
Last Update: Nov 18, 2024
Questions: 291
PK0-005 pdf

PK0-005 PDF

$28  $80
PK0-005 Engine

PK0-005 Testing Engine

$33.25  $95
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$45.5  $130