Question 16

You ran a demand plan and you are reviewing the shipments forecast value measure. It is always zero for a particular item. Identify the root cause of this problem.

Options:

A.

In planning measures catalog, shipment forecast value measure is not enabled at item and organization level.

B.

In plan parameters, Item List Price marked as primary does not have price defined for the particular item.

C.

In plan parameters, shipment forecast value measure expression is not defined.

D.

In planning measures catalog, shipment forecast measure is not enabled at item and organization level.

Question 17

A customer has created a supply plan based on current requirement. Due to changes in third party forecast, the plan must be rerun with these recent updates. However, while this new information became available, existing supply like on-hand inventory and work order completions have also been updated.

Which data refresh option should be used to reflect all these changes in the plan?

Options:

A.

Do not refresh with current data

B.

Refresh with quick refresh option

C.

Refresh with forecast data

D.

Refresh with selected current data

E.

Refresh with current data

Question 18

Which statement order is NOT true about how to effectively address demand at risk?

Options:

A.

Recommendations appear in one of these five categories (or tabs): Expedite Buy Orders. Expedite Planned Orders. Expedite Transfer Orders. Add Resource Availability, and Add Supplier Capacity.

B.

When you accept an expedite recommendation, the order is firmed by using the expedite date as the firm date. So when the plan is run after accepting the recommendation, the planning process assumes the supply is available on the firm date.

C.

Be aware that recommendations to expedite buy orders not only include purchase orders and requisitions, but also planned buy orders.

D.

To maximize effort, use the Recommendations Summary graph and aim for a low number of recommendations with the associated at-risk demand value substantial enough to make a difference in demand fulfillment percentage.

Question 19

You ran a demand plan with the data refresh option "Do not refresh with current data." Identify two true statements. (Choose two.)

Options:

A.

Shipments history data will not be modified.

B.

Forecasting engine will run without advancing the plan date.

C.

Shipments forecast data will not be modified.

D.

Forecasting engine will not run.

E.

Shipments history data will be updated.

Page: 4 / 7
Exam Code: 1z0-1066-23
Exam Name: Oracle Planning and Collaboration Cloud 2023 Implementation Professional
Last Update: Nov 21, 2024
Questions: 109
1z0-1066-23 pdf

1z0-1066-23 PDF

$28  $80
1z0-1066-23 Engine

1z0-1066-23 Testing Engine

$33.25  $95
1z0-1066-23 PDF + Engine

1z0-1066-23 PDF + Testing Engine

$45.5  $130