Question 20

In a transformational program, all projects are on track and delivering their objective. However stakeholders are hesitant to take on the new processes because performance in the current environment may not be representative of actual performance Stakeholders fear that the program will fail to provide the service required.

To assure positive performance in the current environment, the program manager should do which of the following?

Options:

A.

Ensure the new processes will perform better than the current processes

B.

Ask the program steering committee to endorse the new processes and current program schedule and deliverables

C.

Meet with stakeholders to ensure they understand that the expectations for the new processes are superior to the current processes

D.

Discuss concerns with stakeholders and mitigate them by changing the processes that will be delivered

Question 21

After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.

What should the program manager do next?

Options:

A.

Accelerate the projects and components of the program that replace the two legacy systems

B.

Analyze the impact of accelerating the program, and present the pros and cons to the program sponsor

C.

Identify the parts of the program that need to be accelerated and. if it is cost effective and increases benefits realization, implement the change

D.

Create several "what-if" scenarios of alternatives to present to the program sponsor

Question 22

Who prepares the submittals that are reviewed and approved to ensure that the clients design criteria is met in regards to material selection?

Options:

A.

General Contractor

B.

ICT distribution designer

C.

Client

D.

Architect. Engineering, Consultant Team

Question 23

Program A is dependent upon program B lo complete benefits sustainment for two benefits Program A is on track to meet program benefits However program B's program manager has just advised that program B has been closed.

What should program A's program manager update and review first with the stakeholders?

Options:

A.

Benefits sustainment plan

B.

Benefits register

C.

Benefits management plan

D.

Benefits transition plan

Page: 5 / 10
Exam Code: RCDDv14
Exam Name: BICSI Registered Communications Distribution Designer - RCDDv14
Last Update: Nov 23, 2024
Questions: 288
RCDDv14 pdf

RCDDv14 PDF

$25.5  $84.99
RCDDv14 Engine

RCDDv14 Testing Engine

$28.5  $94.99
RCDDv14 PDF + Engine

RCDDv14 PDF + Testing Engine

$40.5  $134.99