During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?
A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week. Which of the following activities would have allowed the project manager to identify and correct this issue in advance?
A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?
Based on the table below:
Which of the following is the critical path if Task B has extended to ten days?