Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

Free PK0-004 CompTIA Updates

Page: 3 / 29
Question 12

During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?

Options:

A.

Ask the team member to move to a different test environment.

B.

Ask the team member to refrain from testing the scenarios.

C.

Revisit the risk management plan and provide corrective actions.

D.

Revisit the contingency plan and provide corrective actions.

Question 13

A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week. Which of the following activities would have allowed the project manager to identify and correct this issue in advance?

Options:

A.

Risk identification

B.

Gate review

C.

Resource allocation

D.

Resource leveling

Question 14

A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?

Options:

A.

Risk identification

B.

Risk quantification

C.

Risk planning

D.

Risk response

Question 15

Based on the table below:

Which of the following is the critical path if Task B has extended to ten days?

Options:

A.

21 days

B.

23 days

C.

24 days

D.

26 days

Page: 3 / 29
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Nov 18, 2024
Questions: 796
PK0-004 pdf

PK0-004 PDF

$28  $80
PK0-004 Engine

PK0-004 Testing Engine

$33.25  $95
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$45.5  $130