Question 32

During a request for proposal (RFP) debriefing, a supplier provides clarification on some of the answers in the RFP that, had they been included, would have increased the supplier's score. In response to this, which of the following is the BEST course of action for the supply manager to take?

Options:

A.

Award part of the contract to the supplier

B.

Cancel the RFP and issue a new RFP

C.

Verify that the supplier understands the RFP process

D.

Regrade the supplier's submission and reevaluate the results of the RFP

Question 33

Which of the following is the PRIMARY reason for holding a business review with a supplier?

Options:

A.

To determine whether the supplier should be moved to the strategic engagement tier

B.

To strengthen the business relationship and to promote collaboration

C.

To ensure that senior executives from both companies meet on a recurring basis

D.

To review the supplier's cost performance relative to goals set for the year

Question 34

ABC, Inc. has a supply management department responsible for placing orders. In spite of this, a designer from ABC's engineering department places an order with Supplier X for several products.

When the shipment arrives, it is rejected by the receiving department, as they cannot verify the order with supply management. To avoid this situation, the designer should have

Options:

A.

notified the supervisor of the engineering department of the immediate need for the item

B.

requested supply management issue an "after the fact" purchase order

C.

coordinated product needs with supply management prior to order commitment

D.

delayed placing the order until after looking at comparable items from other suppliers

Question 35

A company is about to conduct an opportunity assessment review of the items it purchases. Which of the following categories should be analyzed FIRST?

Options:

A.

Low value/high risk and high value/low risk items

B.

High value/high risk and low value/high risk items

C.

High value/low risk and high value/high risk items

D.

Low value/low risk and low value/high risk items

Page: 8 / 23
Exam Code: CORE
Exam Name: Supply Management Core Exam
Last Update: Dec 26, 2024
Questions: 312
CORE pdf

CORE PDF

$25.5  $84.99
CORE Engine

CORE Testing Engine

$28.5  $94.99
CORE PDF + Engine

CORE PDF + Testing Engine

$40.5  $134.99