A copywriter wants to see his incomplete tasks for projects to which he is assigned.
Which steps should the project manager take to create a custom Workfront report with this information?
What occurs when an individual enters a new commit date that is after the original planned date of a task?
A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?
Given this information regarding a Task:
Planned Start Date: May 14
Actual Start Date: May 14
Planned Completion Date: May 20
Projected Completion Date: May 22
Percent Complete: 50%
Duration: 5 Days
Planned Hours: 8 Hours
Status: In ProgressIf today's date were May 19, what would be the Task's progress status?