Question 100

Which of the following is the BEST method to provide quick status updates on project tasks without interrupting project activities?

Options:

A.

Phone call

B.

Interoffice mail

C.

Newsletter

D.

Internal collaboration site

Question 101

A project manager notices several of the action items discussed during a team-building exercise have been ignored by the project team. Although the team-building exercise was well attended and feedback was well received, nothing was accomplished.

To make the meetings more productive, which of the following steps should the project manager take? (Choose two.)

Options:

A.

Get suggestions from the project sponsor.

B.

Schedule more frequent meetings.

C.

Take meeting minutes.

D.

Post an agenda prior to starting the meeting.

E.

Schedule face-to-face meetings.

F.

Make the meetings mandatory.

Question 102

A project manager in a function organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date.

Which of the following should the project manager do NEXT?

Options:

A.

Ask the PMO to mitigate the risk related to insufficient resources.

B.

Ask the functional manager to provide a resource with the same level of allocation.

C.

Remove 20 of allocation of the resource from the secondary project.

D.

Ask the resource to improve performance to target with commitment date.

Question 103

A contract manager is reconciling project invoices and needs to charge work performed by an outside contractor to a general ledger.

Which of the following would be the BEST project document to reference for this information?

Options:

A.

Cost management plan

B.

WBS dictionary

C.

Statement of work

D.

Vendor selection matrix

Page: 25 / 29
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Dec 30, 2024
Questions: 796
PK0-004 pdf

PK0-004 PDF

$25.5  $84.99
PK0-004 Engine

PK0-004 Testing Engine

$28.5  $94.99
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$40.5  $134.99