Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

CompTIA PK0-004 Based on Real Exam Environment

Page: 11 / 29
Question 44

Using Scrum, which of the following are discussed in a daily standup meeting?

Options:

A.

What was done yesterday, what is planned for today, and what roadblocks need to be removed

B.

What was done yesterday, what is planned for the week, and what issues were resolved

C.

What was done yesterday, what is planned for today, and what deliverables were completed

D.

What was done yesterday, what is planned for this week, and what items from the backlog are priority

Question 45

Which of the following elements should be included on a responsibility assignment matrix?

Options:

A.

Responsible, accountable, consulted, informed

B.

Resource, accountable, signoff, input

C.

Responsible, accurate, confidential, informed

D.

Resource, accountable, consulted, informed

Question 46

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

Options:

A.

SCRUM retrospective

B.

Kickoff meeting

C.

Budget baseline

D.

Risk review

Question 47

A stakeholder is unaware of a project’s status.

Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)

Options:

A.

Status report

B.

Organizational chart

C.

RACI matrix

D.

Meeting minutes

E.

Communication plan

Page: 11 / 29
Exam Code: PK0-004
Exam Name: CompTIA Project+ Exam
Last Update: Nov 18, 2024
Questions: 796
PK0-004 pdf

PK0-004 PDF

$28  $80
PK0-004 Engine

PK0-004 Testing Engine

$33.25  $95
PK0-004 PDF + Engine

PK0-004 PDF + Testing Engine

$45.5  $130