Question 72

Tracking the status of each requirement throughout the development and test phases is called:

Options:

A.

Requirements Checking

B.

Requirements Verification

C.

In-Process Review

D.

Requirements Tracing

E.

Phase-End Review

Question 73

Which of the following activities occur when the software developed by an outside organization is ready for delivery?

Options:

A.

Contractual Relations

B.

Acceptance Testing

C.

Operation and Maintenance

D.

B and C only

E.

A, B, and C

Question 74

The amount of effort required to intercouple or interconnect computer systems is referred to as:

Options:

A.

Reusability

B.

Flexibility

C.

Portability

D.

Interoperability

Question 75

The main objectives of process mapping is / are to understand:

Options:

A.

How a process contributes to meeting the organization's mission and goals?

B.

Who is responsible for the process?

C.

How the process interfaces to produce the organization's outcomes?

D.

All of the above

E.

None of the above

Page: 18 / 23
Exam Code: CSQA
Exam Name: CSQA Certified Software Quality Analyst
Last Update: Dec 22, 2024
Questions: 471
CSQA pdf

CSQA PDF

$25.5  $84.99
CSQA Engine

CSQA Testing Engine

$28.5  $94.99
CSQA PDF + Engine

CSQA PDF + Testing Engine

$40.5  $134.99