Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CMQ-OE VCE Exam Download

Page: 14 / 25
Question 56

The first step a customer should take when developing a supply chain should he to establish

Options:

A.

the specific ISO certification that its approved suppliers will need

B.

a supplier rating, system

C.

requirements and specifications for products and services

D.

documented procedures for incoming inspection

Question 57

Before conducting a survey of its readers, a newspaper publisher divided its database into 10 different income levels. The newspaper then drew a sample from each of the income levels. What type of sampling method is the publisher using?

Options:

A.

Random

B.

Statistical

C.

Stratified

D.

Census

Question 58

In order for a self-directed work team to be successful, the individual members must be responsible for

Options:

A.

team management

B.

statistical process control analysis

C.

employee recognition

D.

new member training

Question 59

If an activity time within a critical path is increased, which of the following is most likely to occur?

Options:

A.

The project will be delayed.

B.

Additional resources will have to made available.

C.

Costs will increase.

D.

All activities in the project will be affected.

Page: 14 / 25
Exam Code: CMQ-OE
Exam Name: Certified Manager of Quality/Organizational Excellence Exam
Last Update: Nov 23, 2024
Questions: 348
CMQ-OE pdf

CMQ-OE PDF

$25.5  $84.99
CMQ-OE Engine

CMQ-OE Testing Engine

$28.5  $94.99
CMQ-OE PDF + Engine

CMQ-OE PDF + Testing Engine

$40.5  $134.99