Question 12

A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.

How should the program manager demonstrate the program's progress"?

Options:

A.

Define the key performance indicators (KPIs) for the program's outcome

B.

Invite the key stakeholder to review the program charter and the program objectives

C.

Provide additional program performance reports to the key stakeholder

D.

Maintain the benefits register and provide it to the key stakeholder

Question 13

What is the air change requirement for a tunnel of 610 m (2000 ft) long with a diameter of 3.4 m (11 ft)?

Options:

A.

One complete air change per hour

B.

Two complete air changes per hour

C.

Three complete air changes per hour

D.

Four complete air changes per hour

E.

Five complete air changes per hour

Question 14

A program manager building the world's largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What should the program manager do?

Options:

A.

Finalize the business case and market analysis with the cote program team and present the findings to the chief executive officer for approval

B.

Work with the core program team to conduct a market analysis and make the decision based on the best return on investment

C.

Arrange a meeting with both sponsors and the steering committee to present the market analysis and work through the conflict

D.

Engage the program stakeholders present the market analysis and findings to facilitate the decision on the best option

Question 15

The above performance report shows the earned value (EV) analysis for a program The program director performs a high-level analysis and must present a summary narrative to the steering committee

What do the current findings show?

Options:

A.

Project C is running behind schedule and is over budget, projects A, B and D are on schedule

B.

Project A is running ahead of schedule and is under budget projects B, C and D are behind schedule

C.

The overall program is performing within an acceptable level of variance

D.

Project A is running behind schedule and is over budget projects B, C. and D are on schedule

Page: 3 / 10
Exam Code: RCDDv14
Exam Name: BICSI Registered Communications Distribution Designer - RCDDv14
Last Update: Nov 23, 2024
Questions: 288
RCDDv14 pdf

RCDDv14 PDF

$25.5  $84.99
RCDDv14 Engine

RCDDv14 Testing Engine

$28.5  $94.99
RCDDv14 PDF + Engine

RCDDv14 PDF + Testing Engine

$40.5  $134.99