Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

AVIXA Communications Certifications CTS Exam Questions and Answers PDF

Page: 7 / 14
Question 28

Two computers are connected to a videoconferencing system through a switcher using HDMI cables. Computer content from PC A is being properly transmitted. However, when PC B is selected by the switcher, it does not work through the videoconferencing system. They both work when connected directly to the videoconferencing system or the monitor. The solution is to add a device that enables____management.

Options:

A.

DDC

B.

DHCP

C.

HDCP

D.

TMDS

Question 29

According to the Gantt chart pictured, the Project Manager should wait to start Activity C until which predecessor has been reached?

Options:

A.

Week 3

B.

Week 4

C.

Activity B

D.

Milestone X

Question 30

What should an AV integrator provide to a general contractor to ensure the supporting trades get the AV information that is needed?

Options:

A.

bid drawings

B.

permit drawings

C.

as-built drawings

D.

construction drawings

Question 31

For a design-bid (tender)-build project, the final step for determining the owner's costs for an AV system is

Options:

A.

selecting an Integrator.

B.

performing a needs analysis.

C.

having the owner approve the design.

D.

ensuring the equipment specification is ready for bid.

Page: 7 / 14
Exam Code: CTS
Exam Name: Certified Technology Specialist
Last Update: Nov 21, 2024
Questions: 193
CTS pdf

CTS PDF

$28  $80
CTS Engine

CTS Testing Engine

$33.25  $95
CTS PDF + Engine

CTS PDF + Testing Engine

$45.5  $130