Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

All CORE Test Inside ISM Questions

Page: 14 / 23
Question 56

Which of the following is the FIRST step in the category management process?

Options:

A.

Conduct contract negotiations with strategic and/or preferred suppliers

B.

Develop a strategy to classify suppliers capable of providing material requirements

C.

Conduct market research to understand the supply market

D.

Build the team and project charter and develop a scope of work

Question 57

Which of the following refers to a stakeholder want as opposed to a stakeholder need?

Options:

A.

Requiring thata supplierprovidedelivery schedules that meet the requirements specified inthe contract

B.

Requiring thata supplierprovideaccommodations for the company's representatives duringvisits

C.

Requiring thata supplierprovidethe purchased component at or below the target cost

D.

Requiring thata supplierprovidedetailed specifications for review for the supplied item

Question 58

Which of the following is the PRIMARY reason why companies should consistently update internal purchasing policies?

Options:

A.

Suppliers might believe they can take advantage of an organization that fails to consistently update policies.

B.

Updating policies is a key metric senior management uses to measure the impact of the purchasing organization on the business.

C.

Auditors expect updates on a regular basis to ensure that the company is consistently reviewing procedures.

D.

The company and market place are constantly undergoing changes.

Question 59

A buying organization requires suppliers to maintain an on-time delivery rate greater than 90%. Based on the data below, which of the following can be concluded regarding the delivery performance of these three suppliers?

Supplier A ScoreSupplier B ScoreSupplier C Score

Total Shipments10002000500

Late Shipments6012551

Options:

A.

All threesuppliers have an on-time delivery rate greater than 90%.

B.

SupplierBhas failed to meettheorganization'srequirements.

C.

SupplierChas failed to meettheorganization'srequirements.

D.

SupplierAhas failed to meettheorganization'srequirements.

Page: 14 / 23
Exam Code: CORE
Exam Name: Supply Management Core Exam
Last Update: Nov 21, 2024
Questions: 312
CORE pdf

CORE PDF

$28  $80
CORE Engine

CORE Testing Engine

$33.25  $95
CORE PDF + Engine

CORE PDF + Testing Engine

$45.5  $130