GET 65% Discount on All Products Coupon code: "bigdisc65"
Which Scrum ritual is meant to look back and improve upon the finished Sprint?
Daily Scrum.
Sprint Retrospective.
Sprint Review.
What is the usual length of the time box for the complete Sprint Planning meeting?
Four hours for a 30 day Sprint, one to two hours for a shorter Sprint.
However long it takes to complete the Sprint Backlog.
Never more than two hours, regardless of Sprint length.
How does Agile bring predictability to the Planning process?
By allowing the customers to review the progress often.
By assigning most of the responsibility to the Product Owner.
By making the team self-organized and self-planning.
By providing early visibility into the team's progress.
Which statement describes Release Planning?
After looking at all the stories in the backlog, the team estimates their effort in detail.
The team meets with the customer to negotiate the scope, cost and time of the release.
The team and the Product Owner agree on an initial plan for the delivery of features.
TESTED 21 Nov 2024